Type and tenure of homes
Number of homes: 4
- 2 x 2-Bed properties for affordable rent
- 2 x 2-Bed properties for shared ownership
These homes were built as part of a Section 106 agreement.
Schedule of works
Started on site: 31 March 2023
Completion: August 2024
Funding
Hastoe funding: £844,520
Total cost £979,033
Development partners
- Local authority: Braintree Council
- Parish Council: Finchingfield
- Contractor: Harding Investments and Marfleet construction
- Employer’s Agent: The Design Partnership