Curdridge, Hampshire

8 new homes

Type and tenure of homes

Number of homes:  8

For social rent:

  • 2 x one-bed flats
  • 3 x two-bed houses

For shared ownership:

  • 2 x two-bed houses
  • 1 x three-bed house  

Schedule of works

Start on site: December 2023

Expected completion: July 2025

Funding

Homes England Grant: £652,302 

Total cost: £2,331,055

Development partners

Special features of interest 

This scheme has been a number of years in the planning. Curdridge Parish Council has been a key driver and advocate for the development. The scheme is a rural exception site, delivering much needed social rent and shared ownership homes, prioritised for local people.

All homes are being built to Hastoe's New-Build Standard.

 

Construction Timelapse Footage 

Footage taken from July 2024 to February 2025.